Conduit is done in Zone D and fibre is currently being installed in some of the lines! We’ve got our fingers crossed that our first customers will be surfing the web before the end of the year. Meanwhile, our next zone that we’ll be working on is Zone C, the area west of downtown and south of Uplands. Locates have already started and crews will begin digging and drilling shortly.
After battling through some bitter cold over the past month, our crews will be taking a break for the Christmas Holidays. They’ll be shut down from December 21st until January 3rd and then back at it in the New Year.